Planned Work & Maintenance

Internet Network:

16th and 17th May 2019 - Forest Grove House: Kelly Communications undertake placing, in the front garden, the Openreach cabling through the prepared ducting infrastructure. Then fitting DP Boxes ready for Tenants to book the service providers.

Note: Shirlaw Homes Ltd [Owners] are not contractually obliged to provide either Internet or Freeview to Beals Gold Service Ltd [Landlord]. The Landlord is not contractually obliged to provide Internet or Freeview to their Tenants.   Our Property Maintenance team, however, has completed in Aug 2018 a network infrastructure to all ten apartments. Freeview was installed in Oct 2018. The Property Maintenance team has waited over 6-months for Openreach cabling to be installed. The team will be on site on 16th & 17th May 2019 to oversee the cabling and connecting of the network.

Painting & Decorating:

May 2019 - 200 Kingston Road: Painting & Decorating of 200B to be completed.
Summer 2019 - Forest Grove House: The small side walls of the steps to Gas Boxes will be rendered and painted white. Any final coat rendering and painting.
Summer 2019 - Forest Grove House: Painting of white spaces in Car-Park. [Tenants will then be asked to stick to using the parking spaces allocated to their apartment.]

Gardening:

May 2019 - Forest Grove House: Prepare front corner of garden and then lay final part of lawn once Openreach complete cabling. In May Shrubs will continue to be planted and planting will continue throughout the year under the landscaping plan.

Carpeting:

May 2019 - Forest Grove House: Carpet to be fitted to stairs and communal area once workmen have completed fitting cabling into the Hub/Storeroom on the 1st Floor.

Bin Store:

Summer 2019 - Forest Grove House: Improvements to the bin store area to be undertaken with an addition of front gates and a fencing-in of the bins.

Signage:

Summer 2019 - Forest Grove House: Improved signage to be installed to exterior and interior.